PREMIUM INTERLOCK PAVERS

BI-CON TRI-CON PETRO
     
BI-CON TRI-CON PETRO
     
BRICK ARCH
BRICKS ARCH
 
LAYING INSTRUCTIONS
 
ITEMS REQUIRED FOR LAYING
  • Cutting Machine
  • Alignment bar
  • Rubber Hammer
  • Vibrating Machine
HOW TO LAY
  • Organize all materials like Pavers, Stone Dust, Vibrating Machine and Cutter atlaying site.

  • Keep the Stone Dust with moisture content. Do not use Stone Dust which is 100% dry.

  • Spread the Stone Dust at the laying areas giving appropriate slope to avoid water clogging.

  • A layer of 50mm stone dust should be spreaded for laying of paver blocks.

  • DISHA Premium Pavers are designed with 'NIBS' which provide definite gap between Pavers and helps in water harvesting.

  • Complete laying operations has to be done on the same day. It is important to note that the laying operations should not be done on piece meal basis.

  • Joints should be filled with dry sand, so that it flows better and fills joints effectively.

  • Edge locking : There should be adequate restraint around the perimeter of all paved area to support traffic loads and to prevent the escape of laying course material from beneath the paved surface.

  • For every 10' of the laying area slope of 2" to 3" should be provided.


Note : Colours are indicative only. Shade and thickness variations are inherent properties of this industry.